Chandigarh's Estate Office has been close to auctioning sites in a bulk material market in Sector 56 (West) since early 2025. In February that year the Estate Officer told Hindustan Times the auction would be held "within a month". In August he hoped for the end of October. By June 2026 it had still not begun, and officials gave The Tribune the reason: environmental clearance was pending.

That clearance has now been reported. The Times of India said this weekend that the State Environment Impact Assessment Authority (SEIAA) has cleared the project, with conditions on air, water, noise and waste. TNC could read only the headline and summary line of that report, because the page does not open in the desk's browser, and has not seen the clearance letter. Everything below comes from earlier reports that were read in full.

191 one-kanal plots and 48 booth sites on about 44 acres

The market is being developed over nearly 44 acres at an estimated cost of about ₹20 crore, The Tribune reported on 9 June 2026. The plan has 191 plots of one kanal each and 48 booth sites. Each one-kanal plot may carry a basement and three floors, HT reported in August 2025. An earlier HT report, in February 2025, put the plot count at 200.

In an affidavit to the National Green Tribunal (NGT) in August 2026, the Deputy Commissioner-cum-Estate Officer described the market as SCOs (shop-cum-offices), booths, association offices, warehouses and transport areas, with a total permissible built-up area of 3,20,238.216 sq m. The same affidavit said the Administration acquired 81.675 acres in Sector 56 for a "Bulk Material Market" through a notification dated 4 April 2000. The reports do not say what is planned on the rest of that land.

The clearance rule that held up the auction

A project with a built-up area above 20,000 sq m needs environmental clearance; both newspapers give that as the rule. The permissible built-up area here is about 16 times the threshold, by TNC's arithmetic.

The question went to the NGT. An application before its Principal Bench alleged that work on the site began without clearance and that about 332 trees were felled. The Administration's affidavit, as The Tribune reported it on 28 August, said felling permission came from the Secretary (Forests) on 18 February 2025, and that 305 green trees and 34 dead ones were removed in June 2025 to fence the land. It said 986 saplings were planted at Rajinder Garden, Sector 1, on 5 July 2025, against the 920 recommended.

The Administration also told the tribunal that no construction would resume at the site until final clearance was granted. The reports read do not give the outcome of the NGT case.

A 2018 list of 182 traders, and more than 300 in the market now

The market was first meant for the marble traders working on private land around Dhanas and Sarangpur. HT traced the decision to a 2022 plea in the Punjab and Haryana High Court by the traders' association; the then SDM (Central) had said the Dhanas market was operating in violation of the Punjab New Capital (Periphery) Control Act, 1952.

Surveys in 2016 and 2018 counted 182 marble shops and 20 others. The Administration has placed the list of 182 before the High Court and maintained that only those traders qualify for allotment, according to the Tribune. Officials told the paper the number working there has since passed 300, as spaces were sublet or shared, and that a fresh survey was being considered.

The pool of bidders has widened too. In February 2025 the Administration let furniture traders from Sectors 53 and 54, who had been served eviction notices, take part. "The auction is open to all traders, regardless of their sector," the Estate Officer told HT.

The two papers differ on how large the present marble market is. The Tribune says nearly 200 acres of agricultural land; HT says about 80 acres taken on lease from landowners.

Leasehold is the plan; traders have asked for freehold

The units are proposed to be allotted on a leasehold basis, the Tribune reported in June, and several traders have been demanding a freehold auction instead. No reserve price has appeared in any report read.

Two other leasehold commercial offers in the city went without bids this autumn: the Sector 39 mandi SCO sites and the Chandigarh Housing Board's 79 commercial units. Those were run by other bodies on their own terms. The separate file on converting leasehold commercial and industrial property to freehold is covered in where FAR 2 and freehold stand.

What is still open

No auction date, reserve price or eligibility terms for Sector 56 have been published in the reports TNC read. The fresh survey of traders has not been reported as done.

Site work is also unfinished on the papers' account. HT said in August 2025 that core services were laid and two internal roads remained. In June 2026 the Tribune reported tenders worth ₹16.37 crore for roads and parking, with financial bids still to be opened. The Administration has said traders will be shifted only after the new market is fully developed.

The conditions attached to the clearance will be known once the SEIAA letter is public.

Dealer-posted listings for the city, which are asking prices and not transaction values, are on TNC's Chandigarh page.

Sources

The Tribune, "Chandigarh Admn plans fresh survey before relocation of marble markets", 9 June 2026: tribuneindia.com

The Tribune, "Chandigarh Administration denies illegal felling of trees at proposed bulk material market site", 28 August 2026: tribuneindia.com

The Tribune, "NGT exempts Chandigarh Chief Secy from appearance in tree-felling case", 4 September 2026: tribuneindia.com

Hindustan Times, "Chandigarh accelerates shift of Marble Market to Sector 56", 20 August 2025: hindustantimes.com

Hindustan Times, "Chandigarh administration allows furniture traders to bid for Sector 56 site", 11 February 2025: hindustantimes.com

The Times of India, "Clearing the dust: Sector-56 bulk material market gets green clearance", online on the night of 14-15 November 2026 (headline and summary line only; the full report was not read): timesofindia.indiatimes.com

This article reports what newspapers have published about a government project. It is not investment or legal advice.

Chandigarh's Estate Office has been close to auctioning sites in a bulk material market in Sector 56 (West) since early 2025. In February that year the Estate Officer told Hindustan Times the auction would be held "within a month". In August he hoped for the end of October. By June 2026 it had still not begun, and officials gave The Tribune the reason: environmental clearance was pending.

That clearance has now been reported. The Times of India said this weekend that the State Environment Impact Assessment Authority (SEIAA) has cleared the project, with conditions on air, water, noise and waste. TNC could read only the headline and summary line of that report, because the page does not open in the desk's browser, and has not seen the clearance letter. Everything below comes from earlier reports that were read in full.

191 one-kanal plots and 48 booth sites on about 44 acres

The market is being developed over nearly 44 acres at an estimated cost of about ₹20 crore, The Tribune reported on 9 June 2026. The plan has 191 plots of one kanal each and 48 booth sites. Each one-kanal plot may carry a basement and three floors, HT reported in August 2025. An earlier HT report, in February 2025, put the plot count at 200.

In an affidavit to the National Green Tribunal (NGT) in August 2026, the Deputy Commissioner-cum-Estate Officer described the market as SCOs (shop-cum-offices), booths, association offices, warehouses and transport areas, with a total permissible built-up area of 3,20,238.216 sq m. The same affidavit said the Administration acquired 81.675 acres in Sector 56 for a "Bulk Material Market" through a notification dated 4 April 2000. The reports do not say what is planned on the rest of that land.

The clearance rule that held up the auction

A project with a built-up area above 20,000 sq m needs environmental clearance; both newspapers give that as the rule. The permissible built-up area here is about 16 times the threshold, by TNC's arithmetic.

The question went to the NGT. An application before its Principal Bench alleged that work on the site began without clearance and that about 332 trees were felled. The Administration's affidavit, as The Tribune reported it on 28 August, said felling permission came from the Secretary (Forests) on 18 February 2025, and that 305 green trees and 34 dead ones were removed in June 2025 to fence the land. It said 986 saplings were planted at Rajinder Garden, Sector 1, on 5 July 2025, against the 920 recommended.

The Administration also told the tribunal that no construction would resume at the site until final clearance was granted. The reports read do not give the outcome of the NGT case.

A 2018 list of 182 traders, and more than 300 in the market now

The market was first meant for the marble traders working on private land around Dhanas and Sarangpur. HT traced the decision to a 2022 plea in the Punjab and Haryana High Court by the traders' association; the then SDM (Central) had said the Dhanas market was operating in violation of the Punjab New Capital (Periphery) Control Act, 1952.

Surveys in 2016 and 2018 counted 182 marble shops and 20 others. The Administration has placed the list of 182 before the High Court and maintained that only those traders qualify for allotment, according to the Tribune. Officials told the paper the number working there has since passed 300, as spaces were sublet or shared, and that a fresh survey was being considered.

The pool of bidders has widened too. In February 2025 the Administration let furniture traders from Sectors 53 and 54, who had been served eviction notices, take part. "The auction is open to all traders, regardless of their sector," the Estate Officer told HT.

The two papers differ on how large the present marble market is. The Tribune says nearly 200 acres of agricultural land; HT says about 80 acres taken on lease from landowners.

Leasehold is the plan; traders have asked for freehold

The units are proposed to be allotted on a leasehold basis, the Tribune reported in June, and several traders have been demanding a freehold auction instead. No reserve price has appeared in any report read.

Two other leasehold commercial offers in the city went without bids this autumn: the Sector 39 mandi SCO sites and the Chandigarh Housing Board's 79 commercial units. Those were run by other bodies on their own terms. The separate file on converting leasehold commercial and industrial property to freehold is covered in where FAR 2 and freehold stand.

What is still open

No auction date, reserve price or eligibility terms for Sector 56 have been published in the reports TNC read. The fresh survey of traders has not been reported as done.

Site work is also unfinished on the papers' account. HT said in August 2025 that core services were laid and two internal roads remained. In June 2026 the Tribune reported tenders worth ₹16.37 crore for roads and parking, with financial bids still to be opened. The Administration has said traders will be shifted only after the new market is fully developed.

The conditions attached to the clearance will be known once the SEIAA letter is public.

Dealer-posted listings for the city, which are asking prices and not transaction values, are on TNC's Chandigarh page.

Sources

The Tribune, "Chandigarh Admn plans fresh survey before relocation of marble markets", 9 June 2026: tribuneindia.com

The Tribune, "Chandigarh Administration denies illegal felling of trees at proposed bulk material market site", 28 August 2026: tribuneindia.com

The Tribune, "NGT exempts Chandigarh Chief Secy from appearance in tree-felling case", 4 September 2026: tribuneindia.com

Hindustan Times, "Chandigarh accelerates shift of Marble Market to Sector 56", 20 August 2025: hindustantimes.com

Hindustan Times, "Chandigarh administration allows furniture traders to bid for Sector 56 site", 11 February 2025: hindustantimes.com

The Times of India, "Clearing the dust: Sector-56 bulk material market gets green clearance", online on the night of 14-15 November 2026 (headline and summary line only; the full report was not read): timesofindia.indiatimes.com

This article reports what newspapers have published about a government project. It is not investment or legal advice.

Chandigarh's Estate Office has been close to auctioning sites in a bulk material market in Sector 56 (West) since early 2025. In February that year the Estate Officer told Hindustan Times the auction would be held "within a month". In August he hoped for the end of October. By June 2026 it had still not begun, and officials gave The Tribune the reason: environmental clearance was pending.

That clearance has now been reported. The Times of India said this weekend that the State Environment Impact Assessment Authority (SEIAA) has cleared the project, with conditions on air, water, noise and waste. TNC could read only the headline and summary line of that report, because the page does not open in the desk's browser, and has not seen the clearance letter. Everything below comes from earlier reports that were read in full.

191 one-kanal plots and 48 booth sites on about 44 acres

The market is being developed over nearly 44 acres at an estimated cost of about ₹20 crore, The Tribune reported on 9 June 2026. The plan has 191 plots of one kanal each and 48 booth sites. Each one-kanal plot may carry a basement and three floors, HT reported in August 2025. An earlier HT report, in February 2025, put the plot count at 200.

In an affidavit to the National Green Tribunal (NGT) in August 2026, the Deputy Commissioner-cum-Estate Officer described the market as SCOs (shop-cum-offices), booths, association offices, warehouses and transport areas, with a total permissible built-up area of 3,20,238.216 sq m. The same affidavit said the Administration acquired 81.675 acres in Sector 56 for a "Bulk Material Market" through a notification dated 4 April 2000. The reports do not say what is planned on the rest of that land.

The clearance rule that held up the auction

A project with a built-up area above 20,000 sq m needs environmental clearance; both newspapers give that as the rule. The permissible built-up area here is about 16 times the threshold, by TNC's arithmetic.

The question went to the NGT. An application before its Principal Bench alleged that work on the site began without clearance and that about 332 trees were felled. The Administration's affidavit, as The Tribune reported it on 28 August, said felling permission came from the Secretary (Forests) on 18 February 2025, and that 305 green trees and 34 dead ones were removed in June 2025 to fence the land. It said 986 saplings were planted at Rajinder Garden, Sector 1, on 5 July 2025, against the 920 recommended.

The Administration also told the tribunal that no construction would resume at the site until final clearance was granted. The reports read do not give the outcome of the NGT case.

A 2018 list of 182 traders, and more than 300 in the market now

The market was first meant for the marble traders working on private land around Dhanas and Sarangpur. HT traced the decision to a 2022 plea in the Punjab and Haryana High Court by the traders' association; the then SDM (Central) had said the Dhanas market was operating in violation of the Punjab New Capital (Periphery) Control Act, 1952.

Surveys in 2016 and 2018 counted 182 marble shops and 20 others. The Administration has placed the list of 182 before the High Court and maintained that only those traders qualify for allotment, according to the Tribune. Officials told the paper the number working there has since passed 300, as spaces were sublet or shared, and that a fresh survey was being considered.

The pool of bidders has widened too. In February 2025 the Administration let furniture traders from Sectors 53 and 54, who had been served eviction notices, take part. "The auction is open to all traders, regardless of their sector," the Estate Officer told HT.

The two papers differ on how large the present marble market is. The Tribune says nearly 200 acres of agricultural land; HT says about 80 acres taken on lease from landowners.

Leasehold is the plan; traders have asked for freehold

The units are proposed to be allotted on a leasehold basis, the Tribune reported in June, and several traders have been demanding a freehold auction instead. No reserve price has appeared in any report read.

Two other leasehold commercial offers in the city went without bids this autumn: the Sector 39 mandi SCO sites and the Chandigarh Housing Board's 79 commercial units. Those were run by other bodies on their own terms. The separate file on converting leasehold commercial and industrial property to freehold is covered in where FAR 2 and freehold stand.

What is still open

No auction date, reserve price or eligibility terms for Sector 56 have been published in the reports TNC read. The fresh survey of traders has not been reported as done.

Site work is also unfinished on the papers' account. HT said in August 2025 that core services were laid and two internal roads remained. In June 2026 the Tribune reported tenders worth ₹16.37 crore for roads and parking, with financial bids still to be opened. The Administration has said traders will be shifted only after the new market is fully developed.

The conditions attached to the clearance will be known once the SEIAA letter is public.

Dealer-posted listings for the city, which are asking prices and not transaction values, are on TNC's Chandigarh page.

Sources

The Tribune, "Chandigarh Admn plans fresh survey before relocation of marble markets", 9 June 2026: tribuneindia.com

The Tribune, "Chandigarh Administration denies illegal felling of trees at proposed bulk material market site", 28 August 2026: tribuneindia.com

The Tribune, "NGT exempts Chandigarh Chief Secy from appearance in tree-felling case", 4 September 2026: tribuneindia.com

Hindustan Times, "Chandigarh accelerates shift of Marble Market to Sector 56", 20 August 2025: hindustantimes.com

Hindustan Times, "Chandigarh administration allows furniture traders to bid for Sector 56 site", 11 February 2025: hindustantimes.com

The Times of India, "Clearing the dust: Sector-56 bulk material market gets green clearance", online on the night of 14-15 November 2026 (headline and summary line only; the full report was not read): timesofindia.indiatimes.com

This article reports what newspapers have published about a government project. It is not investment or legal advice.